|
MultiLiner® Installation Procedure
- Prior to the
relining process the pipe has to be cleaned, and any protruding
elements must be removed. Furthermore all protruding lateral
connections have to be grinded and measured.
- The liner is
taken out of the transportation container, and length and wall
thickness are checked.
- The
MultiLiner®
manifold is mounted in the end of the liner that is being pulled
into the pipe.

DN 18"/450 mm
MultiLiner® is prepared
for installation.
- A pulling
guard is mounted, and a device that ensures removal of
condensation water is put in place.
- If a
pre-liner or sliding foil is used it is installed in the pipe at
this time, and it is attached with a plug in the manhole from
which the liner is installed.
- The invert
roller for the winch is mounted. This device protects the steel
cable when the liner is pulled in, and it makes sure that the
liner can be pulled far enough into the manhole where you are
pulling from.
- The winch is
attached to the pulling guard on the MultiLiner manifold.
- The liner is
folded to half of its width, before it is fed into the manhole.
- 3 persons are
normally required when the
MultiLiner®
is pulled in. 2 persons to feed the
MultiLiner®
into the manhole, and one person
inside the manhole to guide it in. It normally takes approx. 20 -
25 minutes to pull 330 ft. (100 meters) of DN 6" - 18" (DN 150mm -
450mm)
MultiLiner®
into place.

A DN16"/400mm
MultiLiner® is folded and pulled in.
- The liner is
pulled through the pipe, until the pulling end of the
MultiLiner®
reaches the middle of the manhole.


The
MultiLiner® is pulled through
- The
MultiLiner®
is
cut off in the exact length, the safety covering is mounted and
the remaining manifold is mounted.
- The inner and
outer temperature sensors are mounted in both manholes as well as
a pressure sensor hose is mounted in the upstream manhole.
- The special
inlet steam hose is mounted to the
MultiLiner®
manifold in the upstream manhole and
connected to the
MultiLiner®
installation unit. The special
outlet steam hose is mounted to the
MultiLiner®
manifold in the downstream manhole
and connected to the gauge station above the manhole.

The
MultiLiner® is
inflated using the combined steam/air hoze.
Note the pressure sensor hose and temperature sensor wires.

The combined
steam/air hose is connected to the outlet gauge station.
- Prior to
starting the installation procedure all temperature sensors and
hoses are checked in the installation unit, i.e. whether they are
functioning as well as whether they are placed correctly in the
manholes.
- The liner is
inflated with air only up to a certain inner pressure.
- Due to the
condensation device mounted in the downstream manifold, all
condensation water is removed from the
MultiLiner®.
- Now the
temperature is raised to a certain level at a certain pressure.
Thereafter another temperature is reached at a certain level. The
last approx. 60 minutes of the curing is made with pure steam at a
certain pressure. Examples of curing times:
DN 8" (DN
200mm) 330 ft. (100 meters) long 3 - 3
1/2
hours
DN 12" (DN 300mm) 330 ft. (100 meters) long 3 - 3
1/2
hours
DN 18" (DN 450mm)
330 ft. (100 meters) long 3
1/2
- 4 hours
DN 24" (DN 600mm) 330 ft. (100 meters) long 4 - 5 hours
DN 40" (DN 1.000mm) 330 ft. (100 meters) long 6 - 6
1/2
hours

Inside and outside
temperatures as well as pressure is easily
monitored and controlled from the
MultiLiner®
control panel.
- After the
curing is completed a short cooling down procedure must be made.
The cooling down normally takes less than 30 minutes in dimensions
smaller than 18" (450mm)
- The hoses and
temperature sensors can now be removed.
- The
MultiLiner®
manifolds can now easily be cut off with an angle grinder.
- The inner
foil is removed by pulling a push rod through the
MultiLiner®,
attaching the inner foil to the end of the push rod and very
easily pulling it out.
- The
MultiLiner®
installation is now completed and the pipe is ready for post
survey.
|